Watch Olivine coming together

Construction at Olivine by Mirvac is progressing well with lots happening onsite.

Key construction activity includes:

Stages 1A to 3 are complete
• Stage 4: Sewer and drainage infrastructure complete. Water services nearing completion. Road works have commenced.
• Stage 5A: Sewer and drainage infrastructure complete. Water services nearing completion.
• Stage 1B wetland: 95% complete with planting to commence

Watch our construction update video below: