Spring has well and truly sprung, and we have had a busy few months of construction onsite at Olivine.

Key construction milestones include:

•    Stage 4: Electrical works have been completed and final sections of the footpath and road pavement have commenced.
•    Stage 5A: Roadworks are nearing completion and electrical works will commence shortly.
•    Stage 9: Earthworks have been completed and sewer and drainage works are continuing.
•    Gumnut Park & Playground is well underway with play tower elements and play spaces being installed for a mid 2020 opening.
•    Olivine Place Café and Community Space is under construction and will open in 2020.
•    Hume Anglican Grammar expansion is underway to accommodate more students for 2020.

Watch our construction update video below and be inspired to begin your life at Olivine.